Progress so far

With only 2 working weeks left until handover, we have been extremely busy on site over the past month working with various trades to help get the project completed. We are pushing and working hard to get the job done in time for the school children to enjoy after the Easter holidays.

The second floor is near completion and we have a final clean of the floor booked in next week. Once this has been completed, we will then close the floor off as a finished product ready for the school to come and review. The first floor is not too far behind, as we have been progressively working our way down and out of the build. The painter is currently adding the final touches, the joiner is busy hanging doors and the carpet tiles have been installed over the weekend.

Tuckers Mechanical and Electrical have been working hard testing and commissioning items ready to handover back to ourselves for use. CTS are continuing to decorate on the ground floor area and get the rooms up to scratch ready to be handed over to the client.

ATL have finished installing the kitchen and the servery ready for the children to enjoy their school meals from their brand new canteen. Internal furniture such as tables, desks and chairs have been positioned within rooms so we can really get a feel of what the classrooms will look like.

Externally we have PBS working hard to get the landscaping complete, with the base course of tarmac being installed to the first phased area.

We have some pre-completion tours booked in this week, where we have invited Councillors, including the Leader and Portfolio Holder, along with school Governors, members of the Humber Education Trust, and our good friends over at the Goodwin Development Trust, for a sneak preview of a very important addition to our Education portfolio.

Over the next two weeks

  • Groundworks to the externals will be ongoing,
  • Roof lights will be installed,
  • M&E will be commissioned and handed over,
  • Painting and decorating will be continued,
  • Furniture will be installed,
  • Carpet tiles and vinyl will be installed,
  • Ground floor doors will be installed,
  • Various sanitary ware will be installed,
  • Streetlights will be up and working,
  • Tarmac will be down,
  • Pre-completion site tours will take place,
  • Handover will be undertaken!