Progress so far

Lincoln Court
The M&E first fix is underway throughout the building, on the ground and first floor. The extension foundations are now 30% complete. Re-roofing of the current building is 60% complete and the soft internal strip is fully complete. Asbestos Floor tile removal is also underway.

Centre of Excellence
The basement has now been fully removed and the ground is back to bare earth. Yorkshire Demolition is continuing with the brick loads away from the site. The hole left by the basement that was removed is now due to be filled in accordance with the current specification. The Sub-station has been dug out and we are ready to pour the concrete. Piling Mat is also due to continue in line with availability on-site to increase the size.

Hob Moor Playing Field
Progress on the field has been excellent with all items on the programme complete barring the turfing and drain connection, these will both be captured in the next 2 weeks.

Over the next two weeks

Lincoln Court
M&E & asbestos removal is continuing and the roof tile removal will commence. Foundations to be 50% complete.

Centre of Excellence
The excavation will start to be filled with stone by Yorkshire Demolition. This will be completed within the next 2 weeks. The sub-station base will be poured and the access road to the site will be widened to allow trucks to pass by the scaffolding, when erected, to the east end of Lincoln court.

Hob Moor Playing Field
The turf will be laid on the playing field and the drainage connection made.