Visit our parent site www.sewell-construction.co.uk
1204
lm
of pipework installed
794
m2
of screed laid
209
crates installed into the attenuation tank

Progress so far

Works are progressing well in the new build with internal walls, electrical & mechanical items being installed and windows & doors being fitted.

Externally the attenuation tank has been formed and the courtyard is now tarmacked. Brickwork is making progress, forming the outside of the build.

Over the next two weeks

Wall installation will continue throughout the build as well as the electrical and mechanical fittings. The roofing is to be sealed and completed with all gutters and pipework installed.

Brickwork will be complete on the external envelope of the building within the next couple of weeks.

Meet the team...

Danny Walker
Site Manager

How long have you been part of Sewell?
I joined Sewell 15 Years ago starting from an Apprentice Joiner working all the way up to a site manager
What do you think about the project?
It is an amazing experience working on my first major project for Sewell and it is great to be part of something that will benefit the local community

Where are you from?
I live in Hull

What do you like to do outside of work?
I love spending time with my family and have a keen interest in brazilian Jiujitsu.