Over the last few weeks we have made good progress with the project.
The mass barrier ceiling has been installed and made way for partition walls. Drylining and partition work has been completed throughout Level 5 and Level 6, which has allowed us to get a first 'mist' coat throughout in readiness for the mechanical and electrical installation.
Builders' works have been formed to allow mechanical and electrical services which will provide the space with the necessary means to operate. Mechanical and electrical containment has started to be installed within the ceiling space.
In a few weeks the ceiling space should be ready for the ceiling grid installation, which will then make way for further mechanical and electrical installation. The main entrance curtain walling has been installed, along with glazing and flashings, which will be complete shortly ready for door automation and access control. We'll also be continuing with the mechanical and electrical installation, and installing ceilings. Additionally, we'll be preparing the flooring with self-level to give a smooth, clean finish ready for the installation of the carpet tiles and vinyl, preparing door openings ready for door installation early next month, and finishing off the curtain walling and main entrance.


How long have you been part of Sewell Construction?
I have been at Sewell Construction for 9 years in total.
What do you think about the project?
It's great to be involved with a project that benefits the research department and students. I am looking forward to handing over the project and seeing it in use.
What University of Leeds projects have you worked on previously?
Over the years I have worked on a number of different projects throughout the University, helping to create more accessible and modernised facilities.