Progress so far
New wall locations have been constructed across all floors forming the new room layouts. Mechanical and electrical works have progressed across all disciplines.
Structural door widening works have continued to all floors.
Over the next two weeks
Mechanical and electrical works will continue, floor finishes will commence and the external facade louvre installation will be competed.