Progress so far

With the initial phased completion for the Ground floor being acheived earlier this month, works are continuing on the upper floors with mechanical and electrical work being completed above ceilings and light fittings being installed. Fires stopping is continuing across the upper floors and where all work is complete above ceilings, the ceiling tiles are being installed.

Over the next two weeks

The work in the following period will be a focus on closing up ceiling voids to allow activities below to progress to a finish which include decoration and preparation for the carpet finishes to be installed.