Progress so far
The scheme has commenced with work being carried out in the basement forming the new Comms room in blockwork. Soft strip work has also commenced to the Ground, First and Second floor with the main activity taking place on the Ground floor.
Over the next two weeks
Work will continue to progress with the soft strip and removal of walls taking place. The mechanical and electrical will commence with the removal of the existing systems in readiness for replacement work to take place.