26640
Bricks laid to date
170
m2
Render applied to blockwork
1183
metres
Skirting fixed to date

Progress so far

Works are progressing in the refurbishment part of the building with kitchens, shower rooms and joinery items being installed. The new extension is developing with walls being plastered and the start of the decorations.

Externally, the building rendering is now complete and the electric supply has now been installed into the building.

Over the next two weeks

Joinery installations will progress and floor finishes will continue across the refurbishment part of the building with final decorations being applied also. In the new extension, work will continue with the installation of internal walls and plastering.

Meet the team...

Jack Donkin
Management Trainee

How long have you been a part of Sewell?
I joined Sewell last year following work experience and completion of my A-Levels
What do you think about the project?
I'm enjoying seeing the different part of construction with both refurbishment and new build.

Where are you from?
I live in East Yorkshire

What do you like to do outside of work?
I enjoy playing sports and play in Fly Half position, I also enjoy boxing and have won the Yorkshire Amateur Boxing Association Championship.

We've joined Twitter!

Click here to follow us on Twitter and see what our teams are getting up from across all of our sites.