Project Summary

We are extremely proud to be working with Align Property Partners and North Yorkshire County Council to deliver the Sherburn Hungate Primary School extension and refurbishment.

The project includes; upgrading works to existing classrooms, reconfiguration of internal rooms to create an extra classroom and a refurbishment of the offices to the reception and the front of the school.

The new extension will create five new classrooms, a staff room, cloakrooms and breakout areas. The extension to the existing hall will create more room with the ability to close off and separate into two rooms with some large bi-folding doors.

We are also carrying out some works to upgrade the car park and playground area. These works are split into three phases and will complete all the works by Spring 2021.

Progress so far

Main extension internal works

  • Plaster boarding is now complete
  • 1st and 2nd fix M&E are complete
  • Plastering is complete
  • Ceiling grid is complete
  • External doors are complete
  • 2nd fix joinery is now 50% complete
  • Painting is 40% complete

 

Hall extension 

  • Steel frame is now complete
  • SFS is now complete
  • Floor screed is complete

External works

  • Drainage works are 80% complete
  • Storage area and paving works are now finished
  • Extended playground works are 60% complete
  • Extended carpark is 40% complete

Guarded tour / Easter Egg hunt

Just before the school broke off for Easter, all 260 children and the staff safely visited the new extension in their class bubbles for a tour cleverly disguised as an Easter egg hunt.
Each child illustrated an Easter egg design and three from each class were selected to be displayed in the new extension. The children throughly enjoyed walking round the building trying to find their eggs! Every child was rewarded with a small Easter egg gifted from The Easter Bunny AKA Sewell Construction. An overall winner was picked for both the younger and older children, who each received a larger novelty egg.
Please note: all COVID social distancing measures were adhered to during the tour.

Over the next few weeks

We plan to…

  • Complete the rendering to the outside of the building
  • Progress with the brickwork on the hall extension
  • Complete 60% of the external paving
  • Install the internal doors, teaching walls, ceiling tiles and vinyl flooring

Click the play for our latest drone footage...