Progress so far
There has been some great progress made on both schemes so far. This involves the following:
Trinity House Academy
- Installation of crane mat in accordance with structural engineers design
- Cabin decant
- Mechanical & electrical de-commissioning
- Lifting operations
Sirius West Academy
- Enabling works
- Installation of foundations
- Lifting operations
- Service installations
A key element of both projects has been the lifting operations. With Trinity House Academy being situated in the heart of Hull it meant that meticulous planning and world class execution had to be delivered by the project team in order to ensure that there was minimal disruption to commuters and pedestrians. All whilst maintaining the usual high standards of Health and Safety.