Progress so far

All works at the academy are now complete and the early works have been handed over, ready for the main extension works to begin.
The internal refurbishment included remodelling the first and second floors, creating new classrooms, science labs and conference facilities. The dining room on the ground floor has been expanded to accommodate the additional student intake this September.
The eastern stair tower has been fully recladded, including additional wall lining for water tightness.
External works at the academy included creating 12 new car parking spaces, a new pedestrian foothpath to the main entrance and a new cycle storage area.

Over the next two weeks

We are gearing up for the new extension starting in September. The extension will create more learning spaces to allow new science labs to be added.

Meet the team...

Ron
Equid Onlooker

How long have you lived in the area?
As long as I can remember
What do you think about the project?
It's been great to see so much activity during the summer, it's usually very quiet!

What do you like to do in your spare time?
Mostly horsing around