Progress so far
The following progress has been made so far:
- Installation of pile mat
- Installation of 18 continual flight auger piles
- Installation of drainage within building footprint
- Installation of padstones within existing wall in preparation for steel frame
- Internal demolition including removal of atrium roof
- Installation of ground beams
- Installation of structural steel frame & pre-cast stairs
- Installation of metal deck flooring & concrete pour to first & roof levels
- Installation of intumescent coatings
- Installation of SFS to parapet level
- Ground floor pour
Click on the image below to see the full picture.